How Measuring Production Daily Raises Profit

Daily production chart showing cost codes tracked against goal

Your job cost report tells you what happened. Measuring production daily tells you what's happening, while there's still time to protect the profit.

That one difference is where most of the money is.

The job cost report is history

I relied on job cost reports for years. They're important. They tell you where the money went.

But they're history. By the time a cost code shows up over budget, the work is done. The crew has moved on. You can learn from it, but you can't fix it.

Profit gets protected while the job is running. That takes a number that shows up the same day.

Five ways daily measuring raises profit

1. Catch a slipping cost code the same day, not at month-end. A cost code that runs over for one day is a conversation with the foreman. One that runs over for a month is a write-down. The earlier you see it, the cheaper it is.

2. Adjust crews and plans tomorrow morning, based on today's numbers. If a crew is behind, find out why tonight. Late material, the wrong crew size, a goal that was off. Tomorrow's plan can fix it. See one more man, or one better plan.

3. Bid from real production rates, not guesses. Every day you measure adds to your history. The next estimate starts from what your crews actually produce. Bids get more accurate in both directions. You stop losing work you should have won, and stop winning work you should have passed on.

4. Back change orders with daily hours and quantities. When the work changes, a daily record shows exactly how it hit the crew. That's a lot stronger than a foreman's memory three months later.

5. Give every crew a daily goal they can see and own. When the crew knows the goal and sees the score, they manage the day themselves. That's where most of the gains come from. Not from the office. From crews who can see the number.

Where it started

We've been at this since 1993. My co-founder and I built the first version for our own concrete company. It was a pre-browser tool written in Multiplan and dBase.

It grew into a web app that syncs with accounting. Today PayCrew brings over 30 years of that experience to contractors in every trade.

The tools changed a lot. The idea didn't. Measure the day, the same day.

What it takes to make it work

Measuring daily only works when the data is good. That comes down to three keys:

  • Simple = Accurate. Cost codes the crew understands.
  • Timely = Daily. Time and quantities in every day.
  • Consistent = Historical. The same codes job after job.

And it works best when the crew shares in the savings they create. Read how self-funding incentives work.

Where the profit really comes from

Most of the profit gains don't come from the office catching problems. They come from crews who can see the number and fix the day themselves. The office helps. The crew wins it.

That's why the score has to reach the crew the same day. A number only the office sees can catch problems. A number the crew sees can prevent them. The second one is where the margin grows, job after job, without anyone working longer hours.

Start measuring

You don't have to change everything at once. Start with one crew and one cost code. Measure units per man-hour every day for a month. Show the crew. Watch what happens.

Then see how daily production by cost code does it for every crew.

More from the blog

Lee Clark, former concrete company owner and PayCrew co-founder

I Built PayCrew for My Concrete Company

I built PayCrew for my own concrete company, and it started with trust. Here are the seven steps we used to get every employee involved.

Concrete crew finishing a slab pour without the owner on site

I Couldn't Be on Every Pour

I owned a concrete company with more than 250 people. Here's what I learned about running crews when the owner can't be on every site.