Know the Score Before You Leave the Jobsite

Phone screen showing a crew's daily production rate in green at the end of the shift

Example: 180 units. 40 man-hours. 4.50.

That's the number a crew should see before they leave the site.

Your crews want to win

I've never met a good crew that didn't want to win. They compete with the crew across town. They brag about the big pour that went perfect. They remember the day everything went wrong.

What most crews don't have is a score. They work hard all day, go home, and find out weeks later, if ever, whether the day was good.

Your crews want to win. Show them the score.

How the number gets made

In CraftBelt, each person enters their own time and the crew's quantity for the day, on the right job and cost code.

PayCrew does the math. Units divided by man-hours, rounded to two decimals. 180 units divided by 40 man-hours is 4.50 units per man-hour.

Then it compares that rate to the goal. Green if they're on goal. Red if they're behind.

That's it. One honest number, and a color anyone can read.

It's live

The number is live. PayCrew combines posted payroll with unposted time as people enter it, so nobody waits for payroll to post to find out how the day went.

That matters more than it sounds. A score that shows up two weeks later is history. A score that shows up before the truck leaves the site is something the crew can act on tomorrow morning.

The conversation changes

Pair that daily feedback with a clear incentive plan, and the conversation on the jobsite changes.

Crews stop asking how many hours they worked and start asking how much they got done.

The foreman talks about tomorrow's setup on the ride home. The crew notices when they're one man heavy. Somebody suggests staging the forms the night before. Nobody had to order any of it. They can see the score, so they play to win.

When people can see the results, they take ownership of them.

Why every person, not just the foreman

I always wanted each person entering their own time, not just the foreman for everyone. It takes a few minutes a day. It's worth it.

When each person enters their own hours and sees the crew's score, they're part of the result. The apprentice learns what the goal is. The journeyman sees his effort counted. Read more in ask the newest apprentice.

Green or red, both are useful

A red day isn't a failure. It's information.

Maybe the goal was wrong. Maybe the material was late. Maybe the crew was short. A red day the crew knows about is a conversation. A red day nobody sees until the job closes is a write-down.

And a green day is a win the crew takes home.

What the foreman does with it

The foreman gets the most from the number. Before he leaves the site, he knows if the day was won. If it wasn't, he already knows the likely reason, because he was there. That's the best time to plan tomorrow: crew size, setup, material, sequence. The fix goes in while the day is still fresh, not two weeks later when the report shows up.

It also gives the foreman something good to say. On a green day, he can tell his crew they won before they climb in the truck. That's a better end to a day than silence.

A few minutes at the end of the day

A few minutes at the end of the day. One honest number. A crew that knows the score tomorrow morning.

See how it works across every job with daily production by cost code.

More from the blog

Construction time ticket and WIP report side by side on a desk

Month-End Starts on Tuesday in the Field

Your WIP statement is only as good as last Tuesday's time ticket. Here's why accurate month-end numbers start with daily entry and approval.